Update on the Pendola Center Fire (updated 11-27-07) |
|
The plans are complete and have been approved by Yuba County. Construction begins the week of December 3, 2007 with scheduled completion August 1, 2008. The first thing happening is the placement of the septic tanks, grease interceptor, and dosing tank. The excavation for the foundation of the kitchen and dining room is next followed by foundation work. Register for the new Networking Site for pictures. |
|
|
||||||||||||||||||||
|
2/10/08 - And it snowed, and it snowed and it snowed!!! Need I say more. Camp is buried in at least 18” of snow. Contractors will be on site this next week to evaluate not only the site, but the roads needed to bring in equipment and supplies. A new plow blade on the camp pick up truck that arrives this week may help the roads improve. KEEP PRAYING!!! |
|
3/5/08 - Well it has stopped snowing (maybe), but there still is about 6” of snow over the entire construction site. As a result, there is no progress. The Bad NEWS... Completion date as been pushed back to November, 2008. |
![]() |
||
|